Capacity calculation and allocation

Electric Pillar

Application of an allocation process of cross-zonal capacity

What is it about?

Two or more TSOs exchanging balancing capacity need to ensure the overall availability of the cross-zonal capacity for the exchange of balancing capacity. This can be done through the allocation of cross-zonal capacity for the exchange of balancing capacity or for sharing of reserves.

There are three different processes for allocating cross-zonal capacity:

  • co-optimised allocation process (Article 40)

  • market-based allocation process (Article 41)

  • allocation process based on economic efficiency analysis (Article 42).

If TSOs opt for applying one of these processes, they need to further specify the relevant bidding zone borders, the timeframe and the duration of the application of the respective methodology.

Legal basis: Article 38(1) of the EB Regulation

Responsibility: two or more TSOs are allowed to apply the methodology for cross-zonal capacity allocation process for the exchange of balancing capacity or sharing of reserves.

Current status: The proposal for the application of the methodology  from frequency restoration reserves with automatic activation submitted by the TSOs of Denmark, Finland and Sweden was approved by ACER in August 2020.The proposal for the application of the methodology for frequency containment reserves and frequency restoration reserves for the Baltic capacity calculation region (Baltic balancing capacity market), submitted by the TSOs of Estonia, Latvia and Lithuania, was approved by the Baltic regulatory authorities in February 2024.

Implementation: The methodology for the Nordic capacity calculation region has been implemented with the go-live of the capacity calculation methodology, according to the CACM Regulation. The methodology for the Baltic capacity calculation region will be implemented once the capacity calculation methodology for the Baltic capacity calculation region is applied according to the CACM Regulation.

Read more on the latest approved proposals for the application of a methodology for a cross-zonal capacity allocation process for the exchange of balancing capacity or sharing of reserves.

Documentation on the approval process of these proposals.

 

Harmonisation of the methodology for allocating cross-zonal capacity for the exchange of balancing capacity or sharing of reserves

What is it about?

This methodology provides a harmonised approach for the processes of allocating cross-zonal capacity for the exchange of balancing capacity or sharing of reserves, which can be applied by any group of TSOs.

The methodology fosters the optimisation of the allocation process and concerns the co-optimised and the market-based allocation process (Article 40 and 41 of the EB Regulation).

The methodology will replace the regional methodologies for allocating cross-zonal capacity to the balancing timeframe.

Legal basis: Article 38(3) of the EB Regulation

Responsibility: all TSOs

Current status: The harmonised cross-zonal capacity allocation methodology was approved by ACER in July 2023. A proposal for amendment was submitted by TSOs on 31 July 2024. After consulting with stakeholders, ACER reviewed the TSOs’ proposal and adopted the amended methodology on 29 January 2025 (Decision 01-2025).

Implementation: The harmonised market-based process is expected to be fully implemented by September 2027 at the earliest. The implementation deadline of the co-optimised allocation process is defined in the single day-ahead coupling algorithm methodology (Article 37 of the Capacity Allocation and Congestion Management Regulation).

Access the latest approved methodology for harmonising processes for allocating cross-zonal capacity for the exchange of balancing capacity or sharing of reserves.

Documentation on the approval process of this methodology:

Methodology for a co-optimised allocation process of cross-zonal capacity

What is it about?

The co-optimised allocation process is based on a comparison of actual market values of cross-zonal capacity for the exchange of energy and of balancing capacity or sharing of reserves. Its methodology describes the associated rules for allocating cross-zonal capacity across timeframes.

The market values is based on the bids of market participants, submitted for day-ahead energy and balancing capacity markets.

The cross-zonal capacity will be allocated across the balancing and day-ahead timeframe to maximise the combined overall welfare gains.

Legal basis: Article 40(1) of the EB Regulation

Responsibility: all TSOs

Current status: The methodology for a co-optimised allocation process was approved by ACER in June 2020.

Implementation: The implementation is on-going.

All TSOs are currently conducting an impact assessment for the implementation of the co-optimised allocation process and will provide the relevant requirements for the singe day-ahead coupling algorithm to Nominated Electricity Market Operators (NEMOs).

NEMOs need to consider this implementation when submitting amendments of the single day-ahead coupling algorithm methodology (Article 37 of the Capacity Allocation and Congestion Management Regulation).

Read more on the latest approved methodology for a co-optimised allocation process.

Documentation on the approval process of this methodology.

 

Methodology for a market-based allocation process of cross-zonal capacity

What is it about?

The market-based allocation process is based on a comparison of market values of cross-zonal capacity for the day-ahead and  balancing timeframe. Its methodology establishes the rules for allocating cross-zonal capacity for the exchange of balancing capacity or sharing of reserves.

While one of the two market values is based on the bids of market participants, the second one is based on a forecast. The cross-zonal capacity is then allocated across the balancing and energy timeframe with the aim of maximising the expected combined overall welfare gains.

Legal basis: Article 41(1) of the EB Regulation

Responsibility: all TSOs in each capacity calculation region

Current status: Methodologies for a market-based allocation process were approved for the Baltic, Core, GRIT, Italy North and Nordic capacity calculation regions.

Implementation: Different regions have different implementation timelines. Some regions have already implemented the methodology, whereas some other are expected to do so by 2025.

Read more on the latest approved methodologies for a market-based allocation process of the respective capacity calculation region.

Documentation on the approval processes of the methodologies for a market-based allocation process of each capacity calculation region.

 

Methodology for an allocation process of cross-zonal capacity based on economic efficiency analysis

What is it about?

The allocation process is based on a comparison of forecasted market values of cross-zonal capacity for the exchange of energy,  balancing capacity or sharing of reserves. Its methodology describes the rules for allocating cross-zonal capacity across timeframes.

The cross-zonal capacity will be allocated across the balancing and energy timeframe to maximise the expected combined overall welfare gains.

Legal basis: Article 42(1) of the EB Regulation

Responsibility: all TSOs in each capacity calculation region

Current status: Methodologies were submitted for the Core, Greece-Italy (GRIT) and Italy North capacity calculation regions.  Core and Italy North were withdrawn during the approval process, while GRIT was approved.

Implementation: No implementation is foreseen.

Read more on the latest approved methodologies for a market-based allocation process of the respective capacity calculation region.

Documentation on the approval processes of the methodologies for a market-based allocation process of each capacity calculation region.

Development of methodologies related to capacity calculation and allocation in balancing timeframe
Documents
See Also

​​

See Also:

Balancing capacity exchanges

Rules and processes for the exchange and procurement of balancing capacity

What is it about?

Transmission System Operators (TSOs) procure the balancing capacity needed at national level. However, to lower the procurement costs, TSOs may opt for exchanging balancing capacity with other TSO(s).

In this case, TSOs  need to develop the rules and processes for the common procurement of balancing capacity, including the specification of the standard product(s) for balancing capacity (Article 25(2)) they intend to exchange, taking into account the available cross-zonal capacity (Article 38(1)) and the operational limits.

Legal basis: Article 33(1) and Article 34(1) of the Electricity Balancing Regulation

Responsibility: two or more TSOs exchanging or mutually willing to exchange balancing capacity

Current status: So far three groups of TSOs have developed rules and processes for the exchange and procurement of balancing capacity:

  • The Frequency Containment Reserves (FCR Cooperation), together with the exemption for transferring the balancing capacity obligations, were approved by the regulatory authorities of Austria, Belgium, France, Germany, Denmark and The Netherlands in December 2018

  • The Frequency Restoration Reserves with automatic activation (Nordic aFRR market), together with the exemption for transferring the balancing capacity obligations submitted by the TSOs of Denmark, Finland and Sweden, was approved by ACER in August 2020.

  • The Frequency Containment Reserves and Frequency Restoration Reserves for the Baltic capacity calculation region (Baltic balancing capacity market), submitted by the TSOs of Estonia, Latvia and Lithuania, was approved by the Baltic regulatory authorities in February 2024.

Implementation: The FCR Cooperation is operational and expanding. The common rules and processes for the Nordic aFRR market have been implemented with the go-live of the capacity calculation methodology for the Nordic capacity calculation region, according to the CACM Regulation. The common rules and process for the Baltic balancing capacity market will be implemented once the capacity calculation methodology for the Baltic capacity calculation region is applied according to the CACM Regulation.

Read more on the latest approved rules and processes for the exchange and procurement of balancing capacity.

Documentation on the approval process of these methodologies.

 

Standard products for balancing capacity

What is it about?

Each TSO may develop specific products for its national procurement of balancing capacity. However, when two or more TSOs exchange balancing capacity, they are required to use standard balancing capacity products from a list developed by all TSOs.

This list defines the characteristics of the standard products for each type of reserve:

  • Replacement reserves

  • Frequency restoration reserves with manual activation

  • Frequency restoration reserves with automatic activation, including the validity period and the minimum duration between the end of deactivation period and the following activation.

Legal basis: Article 25(2) of the EB Regulation

Responsibility: all TSOs

Current status: The list of standard products for balancing capacity was approved by ACER in June 2020.

Implementation: Each TSO intending to use standard balancing capacity products should implement this methodology by December 2021.

Read more on the latest approved list of standard products for balancing capacity.

Documentation on the approval process of this methodology.

Development of methodologies for exchanges of balacing capacity
Documents
See Also

See Also:

Balancing Energy Platforms

Balancing Energy Platforms

Implementation of methodologies related to the establishment of EU's balancing platforms

Implementation frameworks for balancing platforms

The Electricity Balancing (EB) Regulation governs the establishment of three different balancing platforms by requiring transmission system operators (TSOs) to propose implementation frameworks.

Those frameworks include:

  • governance structure
  • processes for operating the platform
  • timeline for its development.
 RR platformmFRR platform (MARI)aFRR platform (PICASSO)Imbalance Netting (IN) process platform
What is it about?

Each TSO using balancing energy from replacement reserves (RR) to balance its system can use this platform to activate bids from across Europe (instead of activating only bids from service providers connecting to its system).

Therefore, the platform allows TSOs to exchange balancing energy from replacement reserves with neighbouring TSOs.

Each TSO using balancing energy from frequency restoration reserves with manual activation (mFRR) for balancing its system can use this platform to activate bids from across Europe (instead of activating only bids from balancing service providers connecting to its system).

Therefore, the platform allows TSOs to exchange balancing energy from frequency restoration reserves with manual activation with its neighbouring TSOs.

Each TSO using balancing energy from frequency restoration reserves with automatic activation (aFRR) for balancing its system can use this platform to activate bids from across Europe (instead of activating only bids from balancing service providers connecting to its system).

Therefore, the platform allows TSOs to exchange balancing energy from frequency restoration reserves with automatic activation with its neighbouring TSOs.

Through this platform, TSOs avoid the simultaneous activation of frequency restoration reserves in opposite directions by netting their demand for balancing energy from frequency restoration reserves.

 

Legal basis

Article 19(1) of the EB Regulation

Article 20(1) of the EB Regulation

Article 21(1) of the EB Regulation

Article 22(1) of the EB Regulation

Responsibility

All TSOs performing the reserve replacement (RR) process (pursuant to Part IV of Commission Regulation (EU) 2017/1485)

All TSOs

All TSOs

All TSOs

Current status

The implementation framework was approved by the relevant regulatory authorities in August 2021 and amended in 2023.

The implementation framework was approved by ACER in January 2020 and amended in September 2022.

The implementation framework was approved by ACER in January 2020 and amended in September 2022 and July 2024.

The implementation framework was approved by ACER in June 2020 and amended in September 2022.

Implementation

The RR platform has been operational since January 2020 but is expected to be discontinued by the end of 2025. Participating TSOs have assessed that  regulatory requirements (such as 15-minute settlement periods and a 30-minute cross-zonal gate closure) would make the RR process increasingly similar to the mFRR one, significantly limiting the benefits of its continuation. 

Implementation deadline: July 2022. The platform is operational and several TSOs are connected. 

Implementation deadline: July 2022. The platform is operational and several TSOs are connected

The platform has been operational since June 2021 and all TSOs are using it.

Related Documents

Latest approved implementation framework for the RR.

Documentation on the approval process of this methodology.

Latest approved implementation framework for the mFRR platform.

Documentation on the approval process of this methodology.

Latest approved implementation framework for the aFRR platform.

Documentation on the approval process of this methodology.

Latest approved implementation framework for the IN platform.

Documentation on the approval process of this methodology.

Find out more on the implementation of the European balancing platforms on ENTSO-E's website.  

Activation purposes of balancing energy bids 

What is it about?

Transmission System Operators (TSOs) receive standard product balancing energy bids from service providers, which they forward to the European platforms for exchanging balancing energy.

These balancing energy bids shape the common merit order list (ranking of available bids) for each platform and can be activated by the respective platform to satisfy TSOs’ balancing energy demand. Each TSO can activate any of these bids for satisfying system constraints.

Legal basis: Article 29(3) of the EB Regulation

Responsibility: all TSOs

Current status: The methodology was approved by ACER in June 2020.

Implementation: Each TSO should implement this classification methodology, once they join the respective European platform.

Read more on the latest approved methodology for classifying the activation purposes of balancing energy bids.

Documentation on the approval process of this methodology.

Pricing of balancing energy and cross-zonal capacity

What is it about?

TSOs receive standard product balancing energy bids from service providers, which they forward to the European platforms for exchanging balancing energy. Each platform activates the most cost-efficient balancing energy bids to satisfy TSOs’ balancing energy demand. The balancing energy price is set according to the marginal pricing principle. These balancing energy prices represent also a reference for pricing the cross-zonal capacity used in the balancing energy’s exchange by each platform. 

Legal basis: Article 30(1) of the EB Regulation

Responsibility: all TSOs

Current status: The methodology was approved by ACER in January 2020.

Implementation: Each TSO should implement this methodology once they join the respective European platform for the exchange of balancing energy. The European platform for the exchange of balancing energy form replacement reserves applied a different pricing methodology (as it became operation before the ACER Decision 01/2020). However, the TSOs using this platform should implement this methodology by 1st July 2022.

Read more on the latest approved methodology for pricing balancing energy.

Documentation on the approval process of this methodology.

Cross-zonal capacity calculation methodology

What is it about?

The capacity calculation methodology describes how TSOs calculate the available cross-zonal capacity for the exchange of balancing energy or for operating the imbalance netting process within the balancing timeframe. The methodology complies with network security standards.

The process consists of the following steps:

  • TSOs define capacity calculation inputs – i.e. common grid models
  • The inputs are used by regional coordination centres to calculate the available amount of cross-zonal capacities either by using a flow-based or coordinated Net Transmission Capacity (NTC) approach, depending on the respective region.

Legal basis: Article 37(3) of the EB Regulation

Responsibility: all TSOs in each capacity calculation region

Current status: Proposals for this methodology need to be submitted from the TSOs of each capacity calculation region by December 2022.

Implementation: No implementation timeline available yet.

See Also:

History

 

The development of the EB Regulation started in 2011 when the Agency started developing the Framework Guidelines on Electricity Balancing. These Framework Guidelines were adopted on 18 September 2012.   

Among other elements, the Framework Guidelines included provisions for the forthcoming development of the Network Code on Electricity Balancing. The Framework Guidelines were essentially aiming for the integration of national electricity balancing markets through the cross-border exchanges of balancing services.

The core element of the Framework Guidelines were the models for cross-border exchanges of balancing energy that should first emerge in different geographical areas and gradually, i.e. within 6 years be integrated into one European platform where all TSOs would have access to different types of balancing energy while taking into account the transmission capacities available between different areas. To enable the creation of such a market, several requirements need to be implemented such as a common set of rights (in particular in terms of access to the balancing markets and in terms of remuneration) and obligations (in particular in terms of balancing responsibility) for all types of market participants (generation and demand). The Framework Guidelines also asked for more efficient procurement and use of balancing reserves.

The Framework Guidelines on Electricity Balancing also required the standardisation and harmonisation of some key balancing elements such as balancing products, balancing energy pricing and imbalance pricing, which are considered as prerequisites before the markets can be fully integrated. The roles and responsibilities of TSOs, Balancing Service Providers and Balance Responsible Parties also need to be harmonised to a large degree to achieve a level playing field for competition in different Member States.

Based on these Framework Guidelines, ENTSO-E was tasked to develop the Network Code on Electricity Balancing. Subsequently, the draft network code was submitted to the Agency for opinion based on which ENTSO-E revised the network code and resubmitted it to the Agency. Finally, the Agency adopted a recommendation to the European Commission to adopt the Network Code on Electricity Balancing subject to specific amendments proposed by the Agency. Following this recommendation, the European Commission further revised the network code, which was then finally adopted as a Commission guideline in November 2017 and entered into force in December 2017.

The detailed dates and documents of the above actions are presented below:

Action 1: 18 September 2012: The Agency adopts the Framework Guidelines on Electricity Balancing

Action 2: 23 December 2013: ENTSO-E submits the Network Code on Electricity Balancing to the Agency

Action 3: 21 March 2014: The Agency adopts the Opinion on the Network Code on Electricity Balancing

Action 4: 16 September 2014: ENTSO-E submits the revised Network Code on Electricity Balancing to the Agency     

Action 5: 20 July 2015: The Agency adopts the Recommendation on the Network Code on Electricity Balancing

A brief historic introduction
Documents
See Also

Electricity Balancing

Electricity Balancing

The EB Regulation

Image
Electricity transmission line

The Electricity Balancing Regulation establishes the common principles for procuring, activating and exchanging of the balancing services.

These binding requirements implement and ensure a proper functioning of the integrated electricity market in the balancing timeframe and regulate the activities of Transmission System Operators (TSOs), national regulatory authorities and ACER.

What are its core elements?

  • Rules for Balancing Service Providers and Balancing Responsible Parties: the terms and conditions related to balancing defined at national level should provide fair, transparent and non-discriminatory rules for all actors involved in the balancing markets, ensuring adequate and fair competition.

  • Exchange of balancing capacity and cross-zonal capacity allocation: these rules enable TSOs to jointly procure and use balancing capacity, forming broader cooperation, benefiting from economic reserve providing resources outside their area.

  • Common European balancing energy platforms: the integration of balancing energy markets is facilitated by European platforms that apply common merit order list to ensure cost-efficient activation of balancing energy bids across Europe.

  • Harmonisation of imbalance settlement: The imbalance settlement is a national mechanism, and its harmonisation at European level provides a consistent application of the rules across member states. This ensures that market participants have the same incentives to deliver energy, increasing the balancing markets’ overall efficiency.

  • Settlement rules between TSOs: The EB Regulation also ensures that all the exchanges between TSOs are settled with common rules, guaranteeing a fair and non-discriminatory approach.

Image
EB Regulation

​​​

Documents
See Also


 

Stakeholders' involvement

​​​​​Development and amendments to CACM Regulation

The CAC​​​M Regulation has been developed in close cooperation with the Agency, ENTSO-E and stakeholders, in order to adopt effective, balanced and proportionate rules in a transparent and participative manner. In accordance with Article 18(3) of Regulation (EC) No 714/2009, the Commission will consult the Agency, ENTSO-E and other relevant stakeholders, before proposing any amendment to this regulation.

 

Development of terms and conditions or methodologies

 

Every proposal for the terms and conditions on methodologies, having a direct effect on stakeholders, should be submitted to public consultation before its submission for regulatory approval, in accordance with Article 12 of the CACM Regulation. The entities responsible for performing the consultation should duly consider the views of stakeholders resulting from the consultation, prior to its submission for regulatory approval. In all cases, a clear and robust justification for including or not the views resulting from the consultation should be developed and published in a timely manner before or simultaneously with the publication of the respective proposal.​
 

Implementation of CACM Regulation

 

Pursuant to Article 11 of the CACM Regulation, the Agency, in close cooperation with ENTSO-E, has established the Market European Stakeholder Committee (MESC), in order to organise stakeholder involvement regarding single day-ahead and intraday coupling and other aspects of the implementation of the CACM Regulation and holds regular meetings with stakeholders to identify problems and propose improvements notably related to the operation and development of the issues described in the CACM Regulation.

Details on the activities of MESC
 

Involvement of stakeholders in the implementation of CACM Regulation
Documents
See Also

Designation of NEMOs

Designation of NEMOs

Designation of Nominated Electricity Market Operators

Articles 4, 5 and 6 of CACM Regulation determine the designation of Nominated Electricity Market Operators (NEMOs). Each Member State needs ensure that at least one NEMOs is designated in each Member State to perform the single day-ahead and single intraday coupling. Each NEMO designated in a territory of one Member State has the right to provide its services in other Member States (i.e. by way of so called “passporting") Exceptionally Member States may refuse the trading services by a NEMO designated in another Member State only in specific, well-defined cases, as stated in Article 4(6) of the CACM Regulation. Moreover, the Member States have the right to revoke the designation of a NEMO, in case the NEMO fails to maintain compliance with the criteria set in Article 6 of the CACM Regulation.​

Documents
See Also

Implementation

acer image

​​​​​​The CACM Regulation sets out specific obligations for NEMOs, TSOs, regulatory authorities and the Agency regarding the development and approval of different terms and conditions or methodologies, which are considered as detailed rules for the operation of Internal Electricity Market in the day-ahead and intraday timeframe. Article 9 of CACM Regulation describes the process of adoption of these terms and conditions or methodologies. In accordance with Article 9(6) of CACM Regulation these terms and conditions or methodologies are divided into European, regional and national. They are developed either by TSOs or NEMOs and in specific cases the cooperation of both is required. A proposal from NEMOs or TSOs should typically be consulted upon in accordance with Article 12 of CACM Regulation and submitted to the concerned regulatory authorities and to the Agency in accordance Article 9(9) of CACM Regulation. The proposal should contain a timescale for implementation and the expected impact on the objectives of the CACM Regulation (Article 3).

Regulation (EC) No 713/2009 has been repealed and replaced by the Regulation (EU) 2019/942 of 5 June 2019 and amends some procedures established by either Regulation (EC) 713/2009 or Regulation (EC) 714/2009.

The ‘old’ proc​edure for adoption of the terms and conditions or methodologies (before 4 July 2019) now applies for only regional and national decision making processes:

The concerned regulatory authorities should take decisions concerning the proposed terms and conditions or methodologies from NEMOs and/or TSOs within six months after the receipt of the proposal. Where the regulatory authorities are not able to approve the proposal, they can request an amendment, which gives the concerned NEMOs or TSOs two months for amending the proposal. Subsequently the regulatory authorities need to approve the amended proposal within two months after receiving the amended proposal. If the regulatory authorities are not able to reach an agreement or upon their joint request, the Agency becomes competent to adopt a decision on the proposal within six months from the referral.

The ‘new’ procedure (after 4 July 2019) now applies for only those terms and condition or methodologies, which are subject to approval by all regulatory authorities, in accordance to Article 9(6) of the CACM Regulation:

The Agency should take decisions concerning the proposed terms and conditions or methodologies from NEMOs and/or TSOs within six months after the receipt of the proposal.

To enable a regular review of the terms and conditions or methodologies, the TSOs or NEMOs responsible for developing these terms and conditions or methodologies may propose amendments to them and submit them for approval to regulatory authorities  or the Agency, respectively.

For the designatio​n of NEMOs and reviewing the existing bidding zone configuration, different rules and procedures apply and are described in more detail in pages​ Designation of NEMOs and Bidding zone​ review.​​​
 

Implementation of guideline on capacity allocation and congestion management
Documents

​The core elements of CACM Regulation are:

  • Opt​imal definition of b​idding zones​. Bidding zones are geographic areas within which electricity exchanges are unrestricted, whereas exchanges between bidding zones require cross-zonal capacity - which is limited. Bidding zones should be defined to prevent structural congestions within a bidding zone. In case the existing bidding zone configuration is not efficient, TSOs need to review the structure and propose a more efficient one.

  • Calculat​ion of capacities between bidding zones​. Capacity calculation should be coordinated among TSOs to become as efficient as possible and transparent for market participants. As a result, TSOs can provide an optimal amount of cross-zonal capacity for allocation in the market.

  • Allocation of cross-zonal capacities​ with market coupling​. The most efficient way to allocate cross-zonal capacity is the use of the Union-wide market coupling, which collects all bids and offers from the bidding zones within the European Union and maximises the economic surplus. For this purpose, NEMOs organize the day-ahead coupling as an implicit auction and the intraday coupling as continuous trading supplemented by numerous implicit auctions. The CACM Regulation also addresses the related post-coupling pr​ocesses​.

  • Management of re​sidual con​gestions​. Physical congestions, which were not prevented by capacity calculation and allocation, need to be managed by coordinated TSOs' actions -i.e. by using countertrading or re-dispatching.​​​

The core elements
See Also

Redispatching and countertrading

​​​​​Coordination of redispatching and countertrading

What is it about?

The methodology describes how TSOs and regional coordination centres of capacity calculation regions manage network congestions at the day-ahead and intraday level. This is done with regionally coordinated application of costly remedial actions, in the so-called ROSC (Regional Operational Security Coordination) process.

This coordination process involves the remedial actions optimisation and coordination in a single day-ahead and multiple intraday operational security assessment rounds (CROSA).

The methodology is closely related with the Regional Operation Security Coordination (ROSC) methodology (Article 76 of the Guideline on Electricity Transmission System Operation).

Legal basis: Article 35 of the CACM Regulation

Responsibility: all Transmission System Operators (TSOs) in each capacity calculation region

Current status: The methodology was approved in all capacity calculation regions.

Implementation: The methodology is currently being implemented in most of the regions and expected to be fully implemented by the end of 2024.

Read more on the latest approved redispatching and countertrading methodologies of the respective capacity calculation region.

Documentation on the approval processes of the RDCT methodologies of each capacity calculation region.

 

Cost sharing for coordinated redispatching and countertrading

What is it about?

The methodology establishes the rules TSOs need to follow to determine the different categories of flows (loop, internal, phase shifting transformers, allocated flows) which created network congestions for each capacity calculation region and how the respective costs are shared among TSOs.

The process

  • Once resolved in the Regional Operation Security Coordination (ROSC) process by engaging the remedial actions, the polluting flows are mapped accordingly.

  • The costs of engaging the costly remedial actions are appointed to the specific TSOs which create the polluting flows.

Legal basis: Article 74 of the CACM Regulation

Responsibility: all TSOs in each capacity calculation region

Current status: The  methodology was approved in all capacity calculation regions except of Italy North.

Implementation: The methodology is currently being implemented in most of the regions along with the redispatching and countertrading methodology. The implementation in all regions is expected by the end of 2024.

Read more on the latest approved RDCT cost sharing methodologies of the respective capacity calculation region.

Documentation on the approval processes of the RDCT cost sharing methodologies of each capacity calculation region.

Development of methodologies related to redispatching and countertrading
Documents
See Also

​​

See Also:

Post-coupling processes

​Fallback procedures

 

Pursuant to Article 44 of the CACM Regulation, each TSO in coordination with all the other TSOs in the capacity calculation region, needs to develop a proposal for fallback procedures and submit it to the concerned regulatory authorities for approval and to the Agency for information.

Action 1: By June 2017, all TSOs from each CCR submitted to the concerned regulatory authorities and the Agency the proposals for fallback procedures. The delay in the submission was caused by the delay in the approval of the MCO plan.

Action 2: By December 2017, the regulatory authorities of the CCRs CHANNEL, HANSA, GRIT and IU approved the respective proposals for fallback procedures.

Action 3: By December 2017, the regulatory authorities of the CCRs BALTIC,  CORE, ITALY NORTH, NORDIC, SEE and SWE requested from their TSOs to amend the respective proposals for fallback procedures.

Action 4: By February 2018, the TSOs of the CCRs BALTIC, ITALY NORTH, NORDIC, SEE and SWE submitted to the concerned regulatory authorities and the Agency the respective amended proposals for fallback procedures.

Action 5: By April 2018, the regulatory authorities of the CCRs BALTIC, ITALY NORTH, NORDIC, SEE and SWE approved the respective amended proposals for fallback procedures.

Action 6: In March 2018, the regulatory authorities of the CORE CCR referred the amended proposal for fallback procedures to the Agency for a decision in accordance with the procedure set out in Article 9(12) of the CACM Regulation. The reason for the referral was that they were not able to reach an agreement on the amended proposal.

Action 7: By May 2018, the TSOs of CCR CHANNEL submitted to the concerned regulatory authorities and the Agency a proposal for amendment of the fallback procedures.

Action 8: In September 2018, the Agency adopted a decision on the amended proposal for the Core CCR fallback procedures.

Action 9: By December 2018, the regulatory authorities of CCR CHANNEL approved the proposal for amendments for fallback procedures.

Action 10: In October 2020, the TSOs of the Core, GRIT and SEE CCR submitted to their concerned regulatory authorities the amended proposals for the fallback procedures.  

Action 11: In December 2020, the regulatory authorities of GRIT CCR approved the amended proposal for fallback procedures submitted by GRIT TSOs.

Action 12: In December 2020, the regulatory authorities of Core CCR referred the amended proposal for fallback procedures to ACER in accordance with Article 9(11) of the CACM Regulation.​​​

You can find documents related to the above actions here.

You can find the exact dates of the above actions in the implementation table here.

You can find the approved fallback procedures here. ​

 

Calculation of scheduled exchanges

 

Pursuant to Articles 43 and 56 of the CACM Regulation, the TSOs which intend to calculate scheduled exchanges resulting from single day ahead coupling and single intraday coupling need to develop a proposal for a methodology for calculation of scheduled exchanges and submit it to all regulatory authorities for approval and to the Agency for information.  

Action 1: By December 2016, the TSOs, which intended to calculate scheduled exchanges, submitted to the concerned regulatory authorities and the Agency the proposal for the methodology for calculating scheduled exchanges.  

Action 2: In September 2017, all regulatory authorities sent a letter to all TSOs requesting that all TSOs should submit to all regulatory authorities the proposal for the methodology for calculation of scheduled exchanges by December 2017.

Action 3: By March 2018, all TSOs submitted to all regulatory authorities and the Agency the proposal for the methodology for calculation of scheduled exchanges.

Action 4: In September 2018, all regulatory authorities requested from all TSOs to amend the proposal for calculation of scheduled exchanges.

Action 5: By December 2018, all TSOs submitted to all regulatory authorities and to the Agency the amended proposal for the methodology for calculation of scheduled exchanges for the day-ahead and intraday timeframes.

 

Action 6: In February 2019, the chair of the Energy Regulators’ Forum, on behalf of all regulatory authorities, requested the Agency to grant a one-month extension for the regulatory authorities’ decision making regarding the amended proposal for the methodology for calculation of intraday scheduled exchanges, pursuant to Article 8(1) of Regulation (EC) No 713/2009, and in March 2019 the Agency granted the extension.

Action 7: By June 2019, all regulatory authorities approved the amended proposal for the methodology for calculation of day-ahead and intraday scheduled exchanges.

You can find documents related to the above actions here.

You can find the exact dates of the above actions in the implementation table here.

You can find the approved scheduled exchanges methodology here.

 

Congestion income distribution

 

Pursuant to Article 73 of the CACM Regulation, all TSOs need to develop a proposal for a congestion income distribution methodology and submit it to all regulatory authorities for approval and to the Agency for information.

Action 1: By August 2016, all TSOs submitted to all regulatory authorities and the Agency the proposal for congestion income distribution methodology.

Action 2: By February 2017, all regulatory authorities requested from all TSOs to amend the proposal for congestion income distribution methodology.

Action 3: By April 2017, all TSOs submitted to all regulatory authorities and the Agency the amended proposal for congestion income distribution methodology.

Action 4: In June 2017, all regulatory authorities referred the amended proposal for congestion income distribution methodology to the Agency for a decision following the procedure set out in Article 9(12) of the CACM Regulation. The reason for the referral was that they were not able to reach an agreement on the proposal.

Action 5: In December 2017, the Agency adopted a decision on the proposal for the congestion income distribution.

The congestion income distribution methodology should be implemented in each respective capacity calculation region at the date of implementation of the capacity calculation methodology in accordance with Articles 20 and 21 of the CACM Regulation.

You can find documents related to the above actions here.

You can find the exact dates of the above actions in the implementation table here.

You can find the approved proposal for the congestion income distribution methodology here.​

Development of methodologies related to post-coupling processes
Documents
See Also

​The Agency maintains this site to enhance public access to information about the approvals of those terms and conditions or methodologies developed under the network codes/guidelines which require coordination of at least two regulatory authorities. The information on this site is for informational purpose only and does not replace the officially adopted text of the terms and conditions or methodologies in the legally binding documents. The information on this site is based on input from regulatory authorities, transmissions system operators and nominated electricity market operators. The Agency’s goal is to keep the information on this site accurate and timely, subject to the provision of the information to the Agency and subject to confidentiality restrictions. If errors are brought to the Agency’s attention, it will contact the relevant information provider and try to correct the errors. However, the Agency accepts no responsibility or liability whatsoever with regard to the information on this site and, where this information is linked to external sites, to the information on those external sites.​​​​

Disclaimer