III.2.22.
In the RRM requirements document, the Agency states that it may give a precise time slot for the testing of an RRM applicant. Will the date for the IT testing be proposed by the market participant or does the Agency plan to give an exact time slot for testing (e.g. some concrete period)?
Answer: The testing is part of the RRM registration process and will be mainly automated. Therefore, no additional communication with ACER will be necessary. Only in exceptional circumstances, the Agency may allocate specific time slots to a particular RRM. In such a case, the Agency will communicate this to the relevant RRM applicant in advance.
Updated:
29/05/2015