III.7.14.

III.7.14.

Do I need to publish a ramping  up / down of the power plant event as inside information?


Answer: Ramping situations that qualify as inside information as per Article 2(1) of REMIT (i.e. a ramping situation of a precise nature which has not been made public , which relates, directly or indirectly, to one or more wholesale energy products and which, if it were made public , would be likely to significantly affect the prices of those wholesale energy products) should be disclosed under Article 4 of REMIT.

Updated: 
30/06/2020