Is there a need for an inside  information publication according to Article 4 of REMIT- if a power plant  is permanently shut down?


Answer: The information about a power plant which is shut down and therefore the capacity which is not going to be allocated on the wholesale energy market anymore, is regarded as information which is required to be made public .